First Dig for the excavation of the building site
foundation hole has been dug
forms are being set for the concrete for the footing
Now its time for the foundation walls
Starting to do some actual framing
More walls go up in the garage and master area
Stairs go in, making progress
The rounded curve of the balcony
roof sheeting and the second floor get framed
Roof sheeting and facia boards go on
Roofing goes on in a weekend
Plumbing and electrical are all done on the inside Sheet rock is going on
Stucco gets started early in the spring
Sheet rock and painting are done now the tiling and finish work get started
Tiling in the shoe/mud room
Kitchen and Dining room floor gets wood laid.
Kitchen and Dining room floor gets wood laid.
Getting ready for countertops
Heated floor in the Master bathroom
Custom metal railing goes on the curved balcony edge.
Stucco color goes on this is the last coat
Two colors of finish stucco
Dining room china cabinet
Hood cabinet and counter tops installed
Dining room light is installed
Jacuzzi tub overlooking the lake
Jacuzzi tub overlooking the lake
Finished and clean ready for move in
Kitchen Dining room complete
Bedroom carpeted, cleaned and ready for move in
Balcony wall painted and finished
Kitchen countertops granite shiny and ready for move in
Dishwasher and refrigerator ready for thier people to come live